Atal Bihari Vajpayee Government Institute of Engineering & Technology is spread across an area of 123.4 Bighas. The students are provided with modern infrastructure and amenities and are taught using the latest technologies to make learning more interesting and fun. Some of the infrastructural facilities include well-ventilated classrooms, girls' hostel, canteen, indoor and outdoor games, wellstocked library, internet connectivity, medical facilities, and CCTVs installed at suitable places. In addition to this, classrooms and labs are well equipped with Smart Boards, Digital Podiums, Smart TVs, Projectors and the latest Softwares.
Administratively approved funds (in Cr. of Rupees) for completed and ongoing works | Funds released to Execution Agencies (Cr.) | Remarks |
---|---|---|
110.04 Cr.(107.44 Cr. Govt. Fund +2.60456 Cr. SWF)
| 57.99 Cr. Out of this, 1.6 Cr. For auditorium work and 0.3845 Cr. for sports complex have been deposited with BSNL out of SWF. 0.9 Cr. out of Govt. fund to JSV for WS Scheme. 0.53 Cr. to PWD for road repair. |
|
Sr. No. | Name of the Building/Work Completed | A/A Amount (in Cr.) | Execution agency | Amount deposited with Execution agency | Physical Progress | Remarks | |
---|---|---|---|---|---|---|---|
Govt.Fund | SWF | ||||||
1 | Engineering (B. Tech wing): A, B, C, D, E, F, & Vertical Extension G&H blocks including auditorium hall) | 26.47 | 0 | BSNL | 26.47 | 100% | Building inaugurated on 23-11-2023 |
2 | 96 Bedded Girls Hostel | 6.28 | 0 | BSNL | 6.28 | 100% | Building inaugurated on 27-09-2022 |
3 | Cafeteria Block | 1.6 | 0 | BSNL | 1.6 | 100% | Building inaugurated on 09-03-2023 |
4 | Interior work of auditorium | 0 | 1.6 | BSNL | 1.6 | 100% | Auditorium inaugurated on 23-11-2023 |
5 | Outdoor Sports Facility (BB, VB Courts) | 0 | 03845 | BSNL | 0.3645 | 100% | August, 2024 |
Total | 34.35 | 1.9845 | 36.3345 |
Sr.No. | Name of the Building/Work Ongoing | A/A Amount (in Cr.) | Execution agency | Amount deposited with Execution agency | Balance Amount to be deposited with Execution agency | Physical Progress | Remarks | |||
---|---|---|---|---|---|---|---|---|---|---|
Govt.Fund | SWF | Work started in | Likely DoC | Others | ||||||
1 | ITI Wing Building | 10.62 | 0 | BSNL | 6.30 | 4.32 | 75% | 17.09.2021 | 31.03.2025 | Funds Req. |
2 | 102 Bedded Boys Hostel | 8.96 | 0 | BSNL | 6.66 | 2.3 | 70% | 26.04.2023 | 31.03.2025 | |
3 | Type-IV Residences (16 No.) | 8.59 | 0 | BSNL | 6.27 | 2.32 | 70% | 17.05.2023 | 31.03.2025 | |
4 | Polytechnic wing Building | 43.99 | 0 | BSNL | 2.43 | 41.56 | 2% | Nov. 2023 | Funds Req. | |
5 | M/T work of institute road from Baagipul to campus | 0 | 0.62 | HPPWD | 0.5321 | 0.093 | 90% | 05.03.2021 | ||
6 | Water Supply Scheme for campus | 0.9072 | 0 | JSV | 0.9072 | 0 | 80% | 07.10.2021 | ||
Total | 73.0672 | 0.626 | 23.0993 | 50.593 |
Amount (in Cr. of Rupees) of A/A for various construction works till date | Amount (in Cr. of Rupees) of works completed till date | Amount (in Cr. of Rupees) of works under going at present | Amount in Cr. of rupees paid till date to various execution agencies for ongoing works | Balance Amount in Cr. of rupees to be paid to various execution agencies for ongoing works | ||||
---|---|---|---|---|---|---|---|---|
BSNL | HPPWD | JSV | BSNL | HPPWD | JSV | |||
110.04 | 36.34 | 73.7 | 57.99 | 0.5321 | 0.9072 | 50.52 | 0.093 | 0 |